Mining

Equinox Gold completes PFS for Aurizona

The after-tax net present value with a 5% discount is $314 million at $1,500/oz. gold and $600 million at $1,800/oz. gold. The cumulative, after-tax net cash flow will be $464 million ($1,500/oz. gold) or $830 million ($1,800/oz. gold). The all-in sustaining cost per ounce will be $844 from 2024 onward, and it will average $1,058/oz. over the life of the project.

Equinox used proven and probable reserves of 32.3 million tonnes grading 1.6 g/t gold, containing 1.7 million oz. in the PFS. Measured and indicated resources (exclusive of reserves) are 18.1 million tonnes grading 1.49 g/t gold, containing 868,000 ounces. The inferred resource is 12.7 million tonnes grading 2.19 g/t gold, containing 895,000 ounces.

Development of the underground mine carries a capex of $154 million, including a contingency of $20 million. The mine will stretch 2.3 km along strike below the Piaba pit. Seven separate mining areas have been identified, and they will be access via  2-km main haulage decline with individual internal ramps. Long hole stoping is planned with rock backfill from either underground development or pit waste.

New pits planned

The new Boa Esperanca pit will be mined and completed this year, providing a total of 900,000 million tonnes of saprolite ore grading 0.81 g/t gold to the mill. It will replace the Piaba East pit, which will be depleted by the end of 2024.

Mining at the Piaba pit will continue until 2032 in four phases plus the crown pillar when underground mining is complete. This pit will provide 18.9 million tonnes of fresh rock grading 1.3 g/t gold to the mill.

The Tatajuba deposit, 4 km west of the Piaba pit, will be mined in two phases, beginning in the fourth quarter of 2023 and into 2024. Mining will then pause until 2027 when the second phase is complete. The PFS says this deposit will provide 2 million tonnes of saprolite, transition material and fresh rock grading 1.39 g/t gold to the mill.

Three kilometres east of the Aurizona mill, the Genipapo South pit will be mined beginning in 2023. Then mining will move to the Genipapo North pit until 2028. Combined, the two pits will develop 670,000 tonnes of saprolite and laterite feed grading 0.82 g/r gold to the mill.

Removal of the crown pillar  in 2031 and 2032 will result in 1.9 million tonnes of fresh rock grading 1.36 g/t gold as mill feed.

Mineral processing

Equinox achieved commercial production at Aurizona in July 2019 after building a new mill and upgrading existing infrastructure. The capital cost was $160 million. The project has produced over 260,000 oz. of gold since then. The 8,000-t/d mill has a conventional crushing and grinding circuit followed a carbon-in-leach (CIL) recovery. Upgrades to the existing powerline, tailings management facility, and waste rock storage are planned.

(This article first appeared in the Canadian Mining Journal)

View Article Origin Here

Related Articles

Back to top button