Mining

Star Diamond battles Rio Tinto’s call to JV meeting

This is not the first spat between the parties, which are embroiled in a long-running dispute over the development of a diamond project in the Canadian province of Saskatchewan.

Saskatoon-based Star Diamond entered in 207 an earn-in agreement with Rio Tinto Exploration Canada, giving the Anglo-Australian miner an option to earn up to a 60% interest in Star-Orion South.

The miners are embroiled in a long-running dispute over the development of a diamond project in the Canadian province of Saskatchewan.

The diamond producer later said Rio overspent on the project located within the Fort a la Corne diamond district and didn’t comply with the terms of the agreement to exercise its options.

Based on a court undertaking, Rio Tinto previously agreed that it would not call or hold a management committee meeting under the JV agreement between the two partners for a 120-day period following the completion of the ten bulk sample trenches – the release notes that this would include processing, diamond recovery, and results reporting.

On February 8, Rio Tinto advised Star Diamond that the 120-day period has started, with plans to call a management committee meeting once the 120 days have passed.

“Compounding its misconduct, Rio Tinto now seeks to wrongfully add to the first joint venture budget approximately $56.2 million of alleged expenditures from 2020 and 2021 that were not part of the `then current work plan’ as of November 6, 2019,” Star Diamond said in the letter.

Rio believes the comprehensive diamond breakage study is not required by the undertaking.

A 2018 preliminary study estimated 66 million carats of diamonds could be recovered from the project over a 38-year mine life.

The project, located 60 km east of Prince Albert, is known to host larger stones, including high-value Type IIa diamonds.