Sabina updates feasibility on 15-year ‘world-class’ project in Nunavut

“Ongoing work over the last five years has enabled us to significantly advance the project through many critical de-risking phases,” Bruce McLeod, Sabina’s president and CEO, said in a release, adding that the latest study “is rigorous and provides a high level of confidence in our project economics…”

Since the release of the 2015 feasibility, the majority of key earthworks has been completed at the site, such as roads and preparations for an underground exploration ramp, with additional project logistics infrastructure construction. A 172-km winter ice road is in place from the marine laydown area to the Goose property and site infrastructure – including fuel tanks, and construction equipment – has been mobilized.

Basic engineering is now complete and detailed engineering is also mostly complete for the process plant. Sabina has engaged an original equipment manufacturer (OEM) to complete the process plant design and is working towards a fixed price contract with a performance guarantee.

Goose includes an all-weather airstrip, an exploration camp, heavy civil equipment and 4 km of all-weather roads within the project.

During mine construction and operations, equipment and materials would be transported to the port by sea during the summer and then hauled to Goose via a winter ice road. People and smaller items could be transported directly to site by air.

With environmental authorizations for constructions and operations in place, the company also has in place a comprehensive framework agreement on land tenure and an Inuit Impact and Benefits Agreement (IIBA).

With the feasibility, Sabina has also reported reserves for the Umwelt, Llama, Goose and Echo deposits at Goose. Open pit reserves total 9.9 million tonnes at 5.27 g/t gold with underground reserves of 8.8 million tonnes at 6.76 g/t gold. Cut-off grades range between 1.6 g/t gold and 4.1 g/t gold.

McLeod added that Sabina has “already started to focus on refreshing the project debt process with a view to obtaining financing to make a production decision this year.”

(This article first appeared in the Canadian Mining Journal)